Construction MilestonesJuly 26, 1972 Contract Award
March 25, 1975 Start long lead fabrication aft fuselage
November 17, 1975 Start long-lead fabrication of crew module
June 28, 1976 Start assembly of crew module
September 13, 1976 Start structural assembly of aft-fuselage
December 13, 1976 Start assembly upper forward fuselage
January 3, 1977 Start assembly vertical stabilizer
August 26, 1977 Wings arrive at Palmdale from Grumman
October 28, 1977 Lower forward fuselage on dock, Palmdale
November 7, 1977 Start of Final Assembly
February 24, 1978 Body flap on dock, Palmdale
April 28, 1978 Forward payload bay doors on dock, Palmdale
May 26,1978 Upper forward fuselage mate
July 7, 1978 Complete mate forward and aft payload bay doors
September 11, 1978 Complete forward RCS
February 3, 1979 Complete combined systems test, Palmdale
February 16, 1979 Airlock on dock, Palmdale
March 5, 1979 Complete postcheckout
March 8, 1979 Closeout inspection, Final Acceptance Palmdale
March 8, 1979 Rollout from Palmdale to Dryden (38 miles)
March 12, 1979 Overland transport from Palmdale to Edwards
March 20, 1979 SCA Ferry Flight from DFRF to Bigs AFB, Texas
March 22, 1979 SCA Ferry flight from Bigs AFB to Kelly AFB, Texas
March 24, 1979 SCA Ferry flight from Kelly AFB to Eglin AFB, Florida
March 24, 1979 SCA Ferry flight from Eglin, AFB to KSC
November 3, 1979 Auxiliary Power Unit hot fire tests, OPF KSC
December 16, 1979 Orbiter integrated test start, KSC
January 14, 1980 Orbiter integrated test complete, KSC
February 20, 1981 Flight Readiness Firing
April 12, 1981 First Flight (STS-1)
(...)
https://myworldweb.com/remembering-space-shuttle-columbia/Space Shuttle Columbia: A New Beginning and Visionwritten by Chris Gebhardt February 1, 2011
(...) These segments were successfully mated together by July 7, and by September 11 her forward RCS (Reaction Control System) pod was completed.
On February 3, 1979, technicians completed combined systems testing on Columbia and proceeded on to completion of airlock door installation by February 16 as well as vehicle post-checkout completion by March 5.
From there, crews conducted closeout inspection and procedures for final acceptance at Palmdale by March 8.
On this same day, Columbia rolled out of her Palmdale construction facility and was transported overland to Dryden for her official unveiling ceremony and mating to the Shuttle Carrier Aircraft (SCA) for the start of the ferry flight to Kennedy on March 9.Final assembly of Columbia began on November 7, 1977. Her Body Flap arrived at Palmdale three months later on February 24, 1978, as did her Payload Bay door segments on April 28. (...)
https://www.nasaspaceflight.com/2011/02/space-shuttle-columbia-a-new-beginning-and-vision/http://www.collectspace.com/ubb/Forum30/HTML/000734.html