"Note as always: All dates/timings below are forecast only and are subject to change as this is a continuing, dynamic mission. Time below indicated in UTC.
GENERAL STATUS
◾ATV vehicle and operations nominal
◾All ATV04 cargo deliveries completed (bags, air, oxygen, fuel, water)
◾Continuation of ATV loading with trash and liquid waste
ATV STATUS
◾Attached dormant mode,
◾Cabin fan switched Off
ATV-CC STATUS and ATV GROUND SEGMENT
◾All ATV-CC systems nominal
◾ATV monitoring and routine attached activities
CARGO and FUEL STATUS
◾Dry cargo : 2 489kg /100% transferred
◾Accepted trash : 1293kg
◾Accepted liquid waste : 438 l
◾Water : 564kg /100% transferred
◾Air (2 tanks) : 66kg /100% transferred
◾Oxygen (1 tank): 33.3kg/100% transferred
◾Refuelling propellant : 860kg/100% transferred
EXECUTED OPERATIONS
◾04 October: Liquid Waste Transfers
◾04 October: Last Air Transfer
NEXT OPERATIONS. MAIN ACTIVITIES
◾11 October: Liquid waste transfer
◾15 October: Second run of JIS08 undocking training
◾17 October: Cargo transfer
◾17 October: ATV PCE and Control Panel installation onboard ISS
◾18 October: Cargo transfer
◾19 October : PCE test between ISS-ESOC Ground Station
◾21 October: Liquid waste transfer
◾22 October: Orbital D1 unberthing (no ATV support)
◾22 October: Liquid waste transfer
◾23 October : Last trash loading and close-out imagery
◾24 October: Reboost #6
◾25 October : ATV items to be kept in ISS removal and hatches closure
◾26 October : (bu) reboost
◾28 October: ATV4 undocking
◾28 October : ATV in freeflight. Phasing manoeuvres
◾31 October : Manoeuvres
◾01 November : TIV manoeuvers
◾02 November : Reentry"