{...} Coś nie wyszedł premierowy start. {...}
Start został przerwany w T 0, gdy główny silnik wyłączył się, nim boostery na paliwo stałe zostały odpalone.
Aborted launch of the H3 Launch Vehicle (H3/TF1)https://twitter.com/ShuttleAlmanac/status/1625313543016054785https://twitter.com/ShuttleAlmanac/status/1626352211558277121https://global.jaxa.jp/press/2023/02/20230217-1_e.htmlhttps://www.nasaspaceflight.com/2023/02/h3-debut-flight/Japan aborts H3 launch moments before liftoffPark Si-soo February 17, 2023
(...) “The main engine was ignited, but side boosters were not,” said the range control center, shortly after the rocket’s pre-announced launch window of 8:37-8:44 p.m. Eastern. “It is expected that it would probably take longer to examine the situation. The status of launch vehicle Test Flight No.1 will be announced to all launch operators as soon as it will be confirmed.”
JAXA also left a short notice on its website: “Further information will be updated on the JAXA website.” The agency didn’t elaborate on what happened. It’s also not known yet how the agency will examine the issue — after rolling back the rocket to the hangar or at the launch pad. (...)
https://spacenews.com/h3-launch-abort/2) Drugą próbę startu H3 zaplanowano na 18 lutego w tym samym oknie startowym co dzisiaj.
EDIT: Brak info o dacie startu
3) EDIT 18.02.23
17 lutego 9:36~10:38 Maszyna do testowania rakiet H3 nr 1. ``Podczas sekwencji automatycznego odliczania, system pojazdu pierwszego stopnia wykrył nieprawidłowość i nie wysłał sygnału zapłonu dopalacza rakiet na paliwo stałe (SRB-3), więc dzisiejszy start został odwołany.'' Nie wystartował, zostanie wystrzelony ponownie, więc nie jest to bynajmniej porażka.
https://twitter.com/makkisse999/status/16265433822429552644)
JAXA Pinpoints Fault That Scuppered H3 Rocket LaunchThe Yomiuri Shimbun 16:03 JST, February 23, 2023
The maiden launch of the H3 rocket was aborted last week because an abnormality in the electrical system that supplies power to the main engine was detected, according to the Japan Aerospace Exploration Agency.
JAXA reported its findings to an expert panel of the Education, Culture, Sports, Science and Technology Ministry on Wednesday.
The agency aims to launch the nation’s new flagship rocket during a window that runs until March 10.
The H3 rocket’s scheduled launch from the Tanegashima Space Center in Kagoshima Prefecture on the morning of Feb. 17 was aborted seconds before liftoff. A control unit detected an anomaly after the main engine ignited, so ignition signals were not sent to the booster rockets.
According to JAXA, the unit controls multiple functions, including power supply to the main engine. Just before the scheduled ignition of the boosters, an electronic circuit that supplies power from a battery for the main engine suddenly shut down.
The system in which the abnormality was detected supplies power to the engine when a switch inside the control unit is turned on by ground control.
It appears highly probable that some sort of problem occurred in the signal transmission between ground control and the switch in question, and the circuit shut down.
JAXA has confirmed there was no damage to the rocket’s fuselage or the government’s Daichi-3 Earth observation satellite that was on board.
“We’ll do everything we can to launch the rocket by March 10,” JAXA H3 rocket project manager Masashi Okada said.
https://japannews.yomiuri.co.jp/science-nature/technology/20230223-93020/5) EDIT 02.03.23
Wykryto anomalię w systemie sterowania pierwszego stopnia rakiety nośnej H3. Jest zatem bardzo prawdopodobne, że nie jest powiązany z segmentem naziemnym ani silnikami SRB-3, jak pierwotnie sądzono. Winowajcą był (prawdopodobnie) przełącznik półprzewodnikowy w podukładzie zasilania elektrycznego silników LE-9.
Trwają starania, by wystrzelenie RN H3 z satelitą ALOS 3 mogło nastąpić 10 marca 2023 r. (okno startowe trwa do 17 marca).
(1/5) JAXA zveřejnila vybrané podrobnosti k přerušení startu nové japonské nosné rakety H3 ze 17. února. Star byl přerušen mezi časem T -6,3 s, kdy byla zahájena startovné sekvence raketových motorů LE-9 a T -0,4 s, kdy mělo dojít k zážehu motorů SRB-3.
(2/5) Při náběhu motorů LE-9 byla splněna podmínka (velikost tahu) k povolení sekvence startu motorů SRB-3. Po něm by normálně následovalo vyslání signálu k zážehu motorů SRB-3 a startu nosné rakety H3.
(3/5) Tato část ale byla přerušena výskytem anomálie, po které automatika zastavila další kroky. Nebyl tak odeslán signál k zážehu motorů SRB-3 a došlo k aktivaci nouzového vypnutí motorů LE-9. Následně byla odpočtová sekvence ukončena.
(4/5) Anomálie byla detekována v systému řízení prvního stupně nosné rakety H3. Nesouvisí tak velmi pravděpodobně s pozemním segmentem ani motory SRB-3, jak se původně myslelo. Na vině byl (asi) polovodičový spínač v subsystému elektrického napájení motorů LE-9.
(5/5) V současné době probíhá dokončení vyšetřování, prohlídka rakety, implementace úprav/protiopatření a příprava nosné rakety H3 ke startu. Je velká snaha dokončit vše tak, aby se start nosné rakety H3 s družicí ALOS 3 stihl 10. března 2023 (startovní okno trvá do 17. března).